Property Law - Delayed Possession

Client Names and Details will not be disclosed by our company.

 Client Name: Mr.A

 

Age & Gender: 40 yrs, Male

 

Service: Corporate Job

 

Problem Statement: Delayed possession of flat also Car parking lot not given in spite of paying 85% amount of his hard-earned money out of pocket by relying on the assurances of the builder. 

 

Detailed Case Description: Delay in possession of Flat (property) in violation of Registered Agreement dated 25/03/2015 that said possession to be given within 18 months. 85% of work was completed during the agreement so full payment was done by the complainant. Refusal to hand over stilt/covered parking, Alterations are done without the consent of allottees in violation of S.14, OC received in October 2019 but RERA possession date is postponed to 2022

 

Documentation: Builder buyer agreement, email correspondence with the builder by the purchaser, Legal notice to the Builder, Builder reply to that legal notice, Postal Receipts.

 

Consultation and Counselling: We advised the client to hold the meetings with the Builder and request for possession of the flat and sort out any confusion over financial issues.

 

Court Hearing / Mediation and Out-of-Court Settlement: Court Hearing before adjudicating authority(MAHA RERA)

 

Outcomes of the Case: Case won & received favorable order for a purchaser.

 

Client Feedback: Client is happy because he got possession of Flat and Car Parking and now he doesn't have to pay additional rent to his landlord and also because he feels relieved after getting frustrated by following up with the builder for almost 4 yrs.

 

Timeline: 11 months.

 

Costs incurred: Around Fifty Thousand to One lakh.